South Cleveland Church approved for dirt road paving

Photo of dirt road paving project
Dirt road paving project in Locust Grove (staff photo)

The dirt road paving project along South Cleveland Church Road has been approved to start construction. The roadway is located between New Morn Drive and Stone Road in the Mt Carmel area of commission district II.

South Cleveland Church is an approved SPLOST IV project. Expenditures to date for design work and property acquisition totaled $123,690.

Construction costs are $1,016,987.44. The lowest bid was awarded to Georgia Asphalt, Inc. in Macon, GA.

Funding available in the project budget is $732,000. Several budget amendments were needed to fund construction and utility relocation. All funds were sourced from other district II transportation projects within SPLOST IV.

The budget amendments were:

  • $29,528 from Mt. Olive Road – Complete
  • $3,984 from Fields Drive – Complete
  • $541 from Floyd Road – Complete
  • $87,036 from Industrial Pkwy at SR 20 – Complete
  • $1,640 from South Mt Carmel Road – Complete
  • $636 from Farmer Drive – Complete
  • $356,635 from SR 155 widening (I-75 to Bill Gardner) – Not active

Budget amendments totaled $480,000. All projects are complete except the SR 155 widening, which is not active. Georgia DOT has budgeted funds for the project.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Blog at WordPress.com.

Up ↑

%d bloggers like this: